← Back to Case Studies

Energy · Low Carbon & Storage

Carrington Long Duration Energy Storage [Liquid air]

Company

Highview

Location

Carrington

Value

£370m

Contract

NEC4 Options A, B and C

Case Study

  • Contract management and NEC contract administration, including change control, payment management, project controls, entitlement analysis
  • Procurement – conditions negotiation, commercial evaluation, award recommendations
  • Commercial management – cost forecasting, value appraisal, claims management
  • Project support – temporary works design, technical support, engineering optimisation
  • Design interface management – FEED support, technical interface between civils and mechanical design, build optimisation

What the client said

“Auxilium's team have extensive experience and a deep knowledge of their areas of expertise, which has proved invaluable in supporting our construction and contract management teams in delivering through challenging and programme-critical circumstances.”

Joel EvansDeputy Project Director, Highview Power

Next Steps

Let's deliver your next project.