Payment in construction: it's really that simple

Envelope from Auxilium Consultancy Services stamped Payment Notice in red, lying on a wooden desk beside a pen

Most payment disputes I see in construction aren't about the value of the work. They're about a notice that wasn't sent, a date nobody checked, or an invoice that was treated as if it did a job it can't do.

That frustrates me, because the rules are short. Parliament set out one payment cycle for every construction contract, and if you follow it, most of the arguments never start.

Where the rules come from

If your contract is a construction contract under the Housing Grants, Construction and Regeneration Act 1996 (the Construction Act)1, its payment terms have to comply with sections 109 to 113. Where they don't, the Scheme for Construction Contracts2 fills the gaps. You can't contract out of it.

This applies in England and Wales, and the Act also covers Scotland, which has its own version of the Scheme. Northern Ireland has its own, very similar, legislation. A few contracts sit outside it, most notably work for a residential occupier on their own home3.

The Act gives the parties a lot of freedom. In its own words, "the parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due"4. As John Uff puts it, "the objective is to facilitate cash-flow and to achieve timely payment"5. What the Act doesn't let you do is leave the mechanics vague.

The cycle, step by step

1. Staged payments. If the work will last 45 days or more, the payee is entitled to be paid in instalments, stages or periods (section 109). Monthly is the norm, but the parties can choose.

2. A due date and a final date. Every contract must have an adequate mechanism for working out what becomes due, and when, and it must set a final date for payment (section 110). The parties agree the gap between the two. The final date is the deadline: the day by which the money has to be in the payee's account.

3. A payment notice within five days. Not later than five days after each due date, the payer (or someone named in the contract, such as the Project Manager or Contract Administrator) must issue a payment notice saying what sum they consider was due and how it was calculated (section 110A). Some contracts flip this round and make the payee give the notice instead. Either way, the sum in a valid notice becomes the notified sum. Zero is allowed, as long as the basis is shown.

4. If the payer stays silent. If no payment notice arrives, the payee can serve its own notice at any time afterwards. The final date for payment then moves back by the same number of days the payee waited (section 110B). Better still for the payee: if the contract lets it submit an application before the payment notice deadline, and it does, that application stands as the notice6. So a payer who says nothing on time is left with the payee's figure.

5. Pay the notified sum, unless you serve a pay less notice. The payer must pay the notified sum by the final date (section 111). If it wants to pay less, it has to give a pay less notice, stating the sum it considers due on the day the notice is served and how that sum is calculated, no later than the period the contract sets before the final date. If the contract doesn't set one, the Scheme does: seven days before the final date7. Miss that window and the notified sum is payable in full8. You can still argue about the true value afterwards, but you have to pay first.

We've written about how expensive getting this wrong can be in a recent LinkedIn post on a case where a pay less notice served on time under the contract was late under the Act and cost the employer over £910,000.

6. The right to suspend. If the notified sum isn't paid by the final date, the payee can suspend some or all of its work after giving at least seven days' notice, saying why. It's entitled to the extra time, and to a reasonable amount for the costs of suspending and restarting (section 112).

7. No "pay when paid". A clause that makes payment depend on the payer being paid by someone else is ineffective, unless that third party is insolvent (section 113). Since 2011, the same goes for clauses that make payment depend on what happens under another contract, the so-called "pay when certified" clauses9.

Invoices are not payment notices

This is the one that catches people out most. An invoice is an accounting document. It can do the job of a payee's notice, but only if it states the sum and the basis on which it was calculated. A bare figure with a VAT number on it doesn't.

And the timetable has to hang off the due date, not the invoice. A final date for payment that moves depending on when an invoice turns up is exactly the kind of clause that fails the Act and drops you into the Scheme's shorter timetable, which is what happened in the case above.

What a good payment process looks like

It really is that simple:

  • the application goes in before the due date, a couple of days early, with the basis of the sum set out
  • the payment notice goes out within five days of the due date, with its basis, every time, even if the figure is the same as the application
  • the notified sum is paid by the final date, unless something genuinely justifies a pay less notice, and that notice goes out in time
  • every date is logged: when each application, notice and payment was sent and received

None of this is complicated. It just has to be done every month, on time, by someone who knows the dates.

If you'd like someone to check your payment terms or set up a payment process that works, get in touch.

Notes

  1. As defined in section 104 of the Act. ↩
  2. The Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649), Part II, as amended in 2011. ↩
  3. Section 106. Section 105(2) also excludes some operations, such as certain work on power generation and process plant. ↩
  4. Section 109(2). ↩
  5. John Uff, Construction Law (12th edition), p. 278. ↩
  6. Section 110B(4). ↩
  7. Section 111(3) to (5) and paragraph 10 of the Scheme. Under the Scheme, the final date for payment is 17 days after the due date (paragraph 8(2)), so the pay less deadline is 10 days after the due date. ↩
  8. Section 111(1). The one exception is where the contract says the payer need not pay if the payee becomes insolvent, and the payee becomes insolvent after the pay less deadline (section 111(10)). ↩
  9. Section 110(1A). Exclusion orders take some contracts outside this rule, such as certain PFI-type project contracts. The 2011 changes apply to contracts entered into on or after 1 October 2011 in England and Wales. ↩